Perlubie / Perlubie South (PEL92)

Permit:

PEL92 (PPL application pending)  
COE Interest: 25%
Participant Status: Non-operator
Permit Type: Exploration (Awaiting PPL approval)
Location: Onshore
Permit Area:  
Award Date:  
Tenure: No expiry
Current Year: 1
Discovered: February 2009
First Production: May 2009
Reservoir: Namur/McKinlay (Jurassic)
Field Area:

approximately 0.7 km2 (Perlubie)

approximately 0.6 km2 (Perlubie South)

 

callawongamap

Click on image to enlarge

Overview

The Perlubie oil field is currently developed by one well. The field commenced production in May 2009. Crude is currently trucked to Moomba. 

The Perlubie South flowline is currently under construction and is due to be commisioned by the end of November 2009.