Perlubie / Perlubie South (PEL92)
|
Permit: |
PEL92 (PPL application pending) | |
| COE Interest: | 25% | |
| Participant Status: | Non-operator | |
| Permit Type: | Exploration (Awaiting PPL approval) | |
| Location: | Onshore | |
| Permit Area: | ||
| Award Date: | ||
| Tenure: | No expiry | |
| Current Year: | 1 | |
| Discovered: | February 2009 | |
| First Production: | May 2009 | |
| Reservoir: | Namur/McKinlay (Jurassic) | |
| Field Area: |
approximately 0.7 km2 (Perlubie) approximately 0.6 km2 (Perlubie South) |
|
Click on image to enlarge
Overview
The Perlubie oil field is currently developed by one well. The field commenced production in May 2009. Crude is currently trucked to Moomba.
The Perlubie South flowline is currently under construction and is due to be commisioned by the end of November 2009.